Booking Schedule of the
(6.0 MeV EN-Tandem, 2.5 MV Van der Graaff, Data - Acquisition Facilities)


Septemeber - 2003
Key
Scheduled
Run after rescheduling
Run as scheduled
Date
(scheduled)
Date
(run)
Project / Institutions Number Spokesperson / team Beam/Energy Facility / DAQ Result
Sep 1-3
 Sep 1-3
Maintainence

O Pekar,
S Masala
,


Compressed air system attention
Installation of extraction system for backing pump exhaust fumes in vault
Sep 6-11
 Sep 6-11
Diamond Detectors
Charge Carrier dynamics

A DaCosta,
E Sideras-Haddad,
SH Connell
3.2 MeV p
Tandem - 30o W beam line
Microprobe 
OMDAQ
IBIC measurements on diamond detectors with feint beam - System development
Sep 12,15-22
 Sep 12,15-22
Maintainence

T Hollander,
R Chirwa
O Pekar,
S Masala
,


Development on Magnetic Flux Meter for Tandem and Potch Accelerators,
Attention to
0o beamlime vacuum.
Attention to Potch line vacuum.
Tests of Fluxmeters

Sep 23
 Sep 23
 uProbe tests with heavy ions
  E Sideras-Haddad
SH Connell
A DaCosta
D Dube,
T Tjebane

12C5+ / 20 MeV
Tandem - 30o W beam line
Microprobe 
OMDAQ
Completed
Sep 25-30
 Sep 25-30
Major Power failure

O Pekar,
S Masala
,
T Hollander,
R Chirwa
O Pekar,
S Masala

 
 
Trace problem to water leak under building. Major repairs necessary

Last updated  : 30 Septemebt 2003