Project / Institutions | Number | Spokesperson / team | Beam/Energy | Facility / DAQ | Result |
Oct 1 - 10 | Maintainance ... continued | O Pekar,
T Hollander E Rood |
Improve machine vacuum, Install new Duo b-pump, Check charge P/S ground in tank, Check charging screen position, Overhaul 860A, install dual GVM system fior stabilisation improvement, Check speed of belt, tension etc. Install new corona points. Re-do all circuits around 110V transformer and interfaces for HE Quads P/S. | ||||
Oct 11 - 31 | Testing | SH Connell
E Sideras-Haddad O Pekar, T Hollander E Rood |
various | Ion sources to beam analysis | Stability deterioiation, HV limit on ternminal down to 2.2MV |
Last updated : 19 November