Booking Schedule of the
(6.0 MeV EN-Tandem, 2.5 MV Van der Graaff, Data - Acquisition Facilities)


July - 2002
Key
Scheduled
Run after rescheduling
Run as scheduled
Date
(scheduled)
Date
(run)
Project / Institutions Number Spokesperson / team Beam/Energy Facility / DAQ Result
 Jul 1-17  Jul 1-17 Install AMS Beam-line components, align, services, electronics, detector, vacuum systems.   SH Connell
Vac Students,
P Aggerholm, E Rood, O Pekar, T Hollander, R Chirwa
E Sideras-Haddad
  Tandem - 45o E beam line  Good progress
 Jul 18  Jul 18 Thin single  crystal  diamond project :          Implantation - anneal and etch lift-off technique   C Levitte
(Schonland)
SH Connell
E Sideras-Haddad
JPF Sellschop
12C / 9 MeV Tandem - 0o "High Energy Heavy Ion Implantation" beam line  Produced buried damage layer by implantation
 Jul 19-31   Commission and test AMS Beam-line   SH Connell
E Sideras-Haddad,
E Rood, O Pekar, T Hollander, R Chirwa
12C / 9 MeV, 
14C  sample
Tandem - 45o E beam line
Collect DAQ
Test gass detector with beam, Attempt separation of  14C, 13C, 14N

Last updated  : 19 Aug 2002
For queries and comments - e-mail Dr SH Connell

       Download the MS-Word booking form for the Schonland accelerator facilities.